Project Name TOTAL - Not Including Prior Years 2024-2025 2025-2026 2026-2027 2027-2028 2028-2029
Wastewater Projects $30,202,575 $10,625,263 $12,277,312 $3,000,000 $100,000 $4,200,000
Water Projects $6,188,000 $250,000 $300,000 $2,700,000 $1,500,000 $1,438,000
Streets Traffic Projects $19,180,000 $3,550,000 $6,700,000 $5,130,000 $1,800,000 $2,000,000
Stormwater / Lagoon Projects $12,500,000 $500,000 $7,000,000 $5,000,000 $0 $0
Parks Projects $28,634,750 $9,642,750 $1,287,000 $4,470,000 $8,210,000 $5,025,000
Building Projects $2,322,054 $1,122,054 $0 $200,000 $500,000 $500,000
Grand Total $99,027,379 $25,690,067 $27,564,312 $20,500,000 $12,110,000 $13,163,000