5-Year CIP Plan Summary
print friendly textonly Share page
5-Year CIP Plan Summary
 
Foster City Chamber of Commerce
Five Year Capital Improvement Project Plan
Project Name TOTAL - Not Including Prior Years 2015-2016 2016-2017 2017-2018 2018-2019 2019-2020
Wastewater Projects $48,839,000 $6,181,000 $9,854,000 $11,441,000 $11,540,000 $9,823,000
Water Projects $3,370,000 $0 $0 $970,000 $2,400,000 $0
Streets/Traffic Projects $6,225,000 $2,045,000 $1,180,000 $1,000,000 $1,000,000 $1,000,000
Stormwater/Lagoon Projects $1,635,000 $1,495,000 $0 $140,000 $0 $0
Parks Projects $9,725,000 $1,575,000 $4,525,000 $1,750,000 $1,100,000 $775,000
Levee Projects $1,000,000 $1,000,000 $0 $0 $0 $0
Grand Total $70,794,000 $12,296,000 $15,559,000 $15,301,000 $16,040,000 $11,598,000